29100 Campus
horzline1

29100 Campus 29100 Update

Open-Air Worship Center

(Building-Steering Ministry Team)


29100 Pavilion Overhead29100 Pavilion Overhead

 

August 25:

REJOICE!!  Structural steel arrived at 9:00 a.m. Monday morning, August 23

We thank the Lord for the very visible progress this week since the steel was delivered Monday morning! And as of Thursday morning, the foreman on the erection crew told me that they should have all of the structural steel in place by the end of this week. Then starting Monday, they will commence work on the sheet metal roofing and related structures. They are still looking at the complete erection of the building in two weeks from today. Weather is always a factor, but we are grateful that that has not been a factor thus far. Meanwhile, please pray for these men who are working very hard on our site in extremely hot weather while manipulating very heavy materials: Larry, Justin, Miguel and Ismael. Ask for their protection as they work on our behalf.

 

First Truck Load of Steel

1st Load of Steel

First piece of steel has gone up!

1st steel Steel pile more steel

As of Wednesday morning, August 25.

Wednesday

First crossbeam up!

1st crossbeam more more

It's Growing!!

getting closer

And Growing!!

getting closer

Closer to done!!

getting closer

 

29100 Update:

 

 

May 6, 2010:

 

 

April 22, 2010:

 

 

April 8, 2010:

 

 

As of Thursday AM (Mar 25, 2010):

 

 

As of Friday Noon (Mar 19, 2010):

 

 

As of Thursday (Mar 11, 2010):

 

 

As of Thursday (Mar 4, 2010):

 

 

As of Thursday, (Feb.28, 2010)

 

 

As of Thursday, (Feb.18, 2010)

 

 

As of Thursday, (Feb.18, 2010)

 


As of Thursday, (Feb.11, 2010)

 

 

As of Thursday, (Feb. 4, 2010)

 

 

As of Thursday, (Jan. 28, 2010)